Incident: The warning that never reached the decider
Module 10 · Incident file · About 35 minutes
What happened
In 2010 Queensland Health, the public health department of the Australian state of Queensland, switched on a new payroll system built by IBM, under a contract between the State and IBM that was run by CorpTech, a separate government technology agency. In 2013 a Commission of Inquiry led by the Honourable Richard Chesterman, a retired Court of Appeal judge, reported on what went wrong (Queensland Health Payroll System Commission of Inquiry, Report, 31 July 2013). The figures below are from that report, in Australian dollars.
The contract with IBM was signed on 5 December 2007, with the new payroll due by 31 July 2008. On 14 March 2010, "after ten aborted attempts", the system went live. The Commissioner calls it "a catastrophic failure": it caused "very many QH staff not to be paid, or to be paid inaccurately". The contract price of $6,194,932.98 rose to $25.7M in payments to IBM alone, through about 220 contract changes. Running the repaired system "required about 1,000 employees to process data in order to deliver fortnightly pays", at an estimated $1.2B over the following eight years. The report says it "may be the worst" failure of public administration in Australia.
This file is not about payroll software. It is about one finding the report returns to again and again: the people who could have stopped the project were never put in front of the facts, with options, in time.