Lab: Run the engagement's delivery machinery end to end
Module 11 · Lab · About 70 minutes · Needs: lessons 1 and 2 of this module (the plan, the logs, change requests, the readiness check, adoption)
What you are building
The lessons each looked at one moment: kickoff, a Thursday review, the Monday of week 12, the check on 6 July. This lab runs the whole engagement through one set of files, from Monday 16 March to Monday 6 July. You keep the plan in working days, a RAID and decision log that replays every change, the change requests, a steering pack built from those files, a handover gate, and the one-month review against the target.
Each piece ends in a check written in plain Python, and the last step saves the lot to harbourline-claims/delivery/. There is no model call: every step is bookkeeping that is easy to get wrong on a busy Thursday and easy to check in code. Everything at Harbourline is simulated.